Dateโ
Flight Log contain information relating to steps completed on 06/09/2023
Key Accomplishmentsโ
- We had a working session with the IBM Dev team to show them the issues we are experiencing.
- We decided to go back to using NGINX and validated the secret and certificate were created successfully.
Challengesโ
- We were still experiencing the same issues, so we set up tracelogs for the Ingress and exported these logs for further review.
Action Itemsโ
- We are going to let the IBM Dev team review the logs from today to see if there is any lead on what the issue could be.
Trackingโ
- TS013093278
- [TS013196946] - Another open case
- ibm-client-engineering/solution-filenet-aws#8
- Flight log was added by PR 06-12-2023